Dwarka Expressway Update: Delhi Stretch Nears Completion, Gurgaon Opening Delayed

February 16, 2024 Admin

The Dwarka Expressway, touted as India's first urban elevated highway, continues to be a topic of mixed news, with progress on certain sections overshadowed by delays in others. Here's a summary of the latest updates:

The Dwarka Expressway, touted as India's first urban elevated highway, continues to be a topic of mixed news, with progress on certain sections overshadowed by delays in others. Here's a summary of the latest updates:

 

Delhi stretch:

  • Good news for Delhites! As per NHAI officials, the first two packages of the Dwarka Expressway within Delhi are nearly complete, with over 80% of the work finished.
  • Packages 3 and 4 are undergoing a safety audit before their planned opening in January 2024.
  • It significantly reduces travel time for commuters using the congested NH-48.

 

Gurgaon stretch:

  • While the Delhi section looks promising, news from Gurgaon isn't as optimistic. The initial February 2024 opening deadline for the Gurgaon portion has been pushed back.
  • Recent reports suggest safety audits on packages three and four are still ongoing, delaying the opening. However, the Haryana administration remains hopeful for a March 2024 launch.

 

Overall project:

  • Despite the Gurgaon delay, the entire Dwarka Expressway is still expected to be operational by August 2024.
  • This ambitious project, touted as India's first 8-lane urban elevated highway, promises to revolutionize connectivity between Delhi and Gurgaon, easing traffic congestion and boosting economic activity.

 

Challenges and Delays:

  • Safety audit delays: Packages three and four in Gurugram are undergoing a safety audit, delaying their opening from the earlier January 2024 target. No new opening date has been announced.
  • Cost overruns: A government audit revealed the project's cost has ballooned to 14 times the initial estimate, raising concerns about transparency and project management.
  • Political criticism: The Delhi Lt Governor has criticized delays in the project, calling it an example of inefficiency and highlighting the impact on other important infrastructure initiatives.

 

 

Other developments:

  • Cost concerns: A government audit revealed the project cost exceeding the approved amount by 14 times. Investigations are ongoing.
  • Interstate bus terminal: Haryana Transport Department plans to build a terminal near the expressway in Gurgaon to enhance connectivity.
  • Delhi-Gurugram travel: NH-48 closure for 90 days (ending February 22nd) has increased traffic on alternative routes.

The Dwarka Expressway is a complex project facing both progress and setbacks. While certain sections are nearing completion and will offer relief to commuters, concerns remain regarding cost overruns, delays, and transparency. Stay tuned for further updates as the project unfolds.


Dwarka Expressway Delhi Gurugram NCR traffic infrastructure opening date construction progress safety audit cost escalation interstate bus terminal
  • Crisil
  • RERA Registered
  • TNRECA
  • APPCC
  • NAR
Call WhatsApp Post Requirement Enquire
Call WhatsApp Site Visit Enquire
Call WhatsApp Site Visit Enquire
Call WhatsApp Site Visit Enquire
Call WhatsApp Site Visit Enquire